Two GE LMS100 natural gas-fired turbines
| Capital Expenditure and Schedule Progress as of 12/31/2010 | |||
Expenditures |
Procurement |
Construction |
Construction completed |
$182.8 million |
100% |
84% |
53% |
Land acquired; significant city and county agreements finalized - 7/2010
Site grading complete - 7/2010
Air permit issued by CO Department of Public Health and Environment - 7/22/2010
Began full construction activity - 7/22/2010
Mechanical contracts awarded - 9/22/2010
Substation access road construction completed - 9/2010
2 LMS foundations completed - Q4 2010
1st LMS100 gas turbine delivered - 10/21/2010
Generator step up transformers delivered - 10/21/2010
2nd LMS100 gas turbine delivered - Q4 2010
Electrical contracts awarded - Q4 2010
Cooling towers delivery - Q4 2010
First firing of natural gas turbines - Q3 2011
Commercial operation - January 1, 2012
| Capital Expenditure and Schedule Progress as of 12/31/2010 | |||
Expenditures |
Procurement |
Construction |
Construction completed |
$162.6 million |
100% |
71% |
33% |
Land acquired; significant city and county agreements finalized - 7/2010
Site clearing and grading complete - 7/2010
Air permit issued by CO Department of Public Health and Environment - 7/22/2010
Began full construction activity - 7/22/2010
Mechanical contracts awarded - 9/22/2010
Electrical contracts award - Q4 2010
Cooling towers delivery - Q4 2010
Foundation complete - Q4 2010
Delivery of four GE LM6000 natural gas turbines - Q1 2011
Generator step up transformers delivery - Q1 2011
Delivery of two 20 MW steam turbines - Q1 2011
First firing of natural gas and steam turbines - Q3 2011
Commercial operation - January 1, 2012